BCN Industry Tracker
BCN POTS & Copper Retirement Tracker
Carrier copper and POTS retirement by state, county and wire center: FCC filings, deadlines and the business systems affected. Select a state to drill in.
Data updated
Current, next update November 24, 2026
24
States with confirmed FCC filings
274K+
Customer locations covered by confirmed filings
49
States and territories with an active carrier footprint
190
Days to the next authorized shut-off (Jun 1, 2027)
United States Wisconsin Douglas County
Skip the map and go to the county table
- FCC approved
- Filed
- Not named in any filing
Select a county for its wire centers and shut-off date. On a small screen the county table below is easier to use than the map.
Wisconsin
Confirmed: FCC approved
Shut-off authorized 265 days ago
- Carrier
- AT&T
- Docket
- WC Dockets 25-228, 25-327, 25-335, 26-98, 26-143, 26-192, 26-210, 26-224, 26-276, 26-293
- Earliest shut-off
- On or after Mar 3, 2026
- Not yet placed in a county
- 2
- Status
- Part of AT&T's 21-state legacy ILEC territory. AT&T stopped accepting new copper POTS orders here Oct 15, 2025 and is rolling out wire-center-level Section 214 filings under the FCC's streamlined process; targeting retirement of the "large majority" of its copper outside California by end of 2029.
Counties named in filings: 27 of 72, 39 wire centers
Select a county on the map, or in the county table below, to see its wire centers. Grey counties are not named in any FCC discontinuance filing loaded here.
Not yet placed in a county (2)
Named in a filing, but no public place record puts them in one county yet. A person places them; until then they apply somewhere in this state.
- New London (NWLNWI11, WC 25-335, WC 26-98)
- Waupun (WAPNWI11, WC 25-335)
Filed, list not loaded yet: AT&T WC 26-210. The places it covers are listed only in the carrier's application, which has not been loaded here yet.
Filed, list not loaded yet: AT&T WC 26-224. The places it covers are listed only in the carrier's application, which has not been loaded here yet.
Filed, list not loaded yet: AT&T WC 26-276. The places it covers are listed only in the carrier's application, which has not been loaded here yet.
Filed, list not loaded yet: AT&T WC 26-293. The places it covers are listed only in the carrier's application, which has not been loaded here yet.
Also filed: Verizon (Frontier) WC 26-170, legacy voice throughout its former Frontier service areas, on or after Nov 16, 2026; the filing names no counties.
Adams County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Adams County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Ashland County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Ashland County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Barron County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Barron County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Bayfield County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Bayfield County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Brown County
FCC approved
Shut-off authorized 265 days ago
- Filing / docket
- WC Dockets 25-327, 26-143, 26-192
- Earliest shut-off
- On or after Mar 3, 2026
- Carrier
- AT&T
Places named: 3
- De Pere FCC approved
- Green Bay-Ridge Filed
- Kaukauna Wire-center boundary reaches this county Filed
Buffalo County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Buffalo County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Burnett County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Burnett County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Calumet County
Filed
Shut-off authorized 265 days ago
- Filing / docket
- WC Docket 26-192
- Earliest shut-off
- On or after Oct 16, 2026
- Carrier
- AT&T
No wire center, exchange or city named in a filing is in Calumet County itself. The Census blocks in the application, or the state's telephone exchange map, show the places below reaching into it, so some addresses here may be served by them.
Places named: 1
- Kaukauna Wire-center boundary reaches this county Filed
Chippewa County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Chippewa County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Clark County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Clark County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Columbia County
FCC approved
Shut-off authorized 265 days ago
- Filing / docket
- WC Docket 25-228
- Earliest shut-off
- On or after Jun 30, 2026
- Carrier
- AT&T
Places named: 1
- Columbus Wi FCC approved
Crawford County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Crawford County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Dane County
FCC approved
Shut-off authorized 265 days ago
- Filing / docket
- WC Dockets 25-228, 25-335, 26-192
- Earliest shut-off
- On or after Jun 30, 2026
- Carrier
- AT&T
Places named: 3
- Madison Filed
- Madison-Spring FCC approved
- Stoughton FCC approved
Dodge County
FCC approved
Shut-off authorized 265 days ago
- Filing / docket
- WC Docket 25-335
- Earliest shut-off
- On or after Nov 15, 2026
- Carrier
- AT&T
Places named: 4
- Beaver Dam FCC approved
- Horicon FCC approved
- Juneau FCC approved
- Mayville FCC approved
Door County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Door County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Douglas County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Douglas County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Dunn County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Dunn County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Eau Claire County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Eau Claire County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Florence County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Florence County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Fond du Lac County
FCC approved
Shut-off authorized 265 days ago
- Filing / docket
- WC Docket 25-228
- Earliest shut-off
- On or after Jun 30, 2026
- Carrier
- AT&T
Places named: 1
- Van Dyne FCC approved
Forest County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Forest County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Grant County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Grant County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Green County
FCC approved
Shut-off authorized 265 days ago
- Filing / docket
- WC Docket 25-228
- Earliest shut-off
- On or after Jun 30, 2026
- Carrier
- AT&T
No wire center, exchange or city named in a filing is in Green County itself. The Census blocks in the application, or the state's telephone exchange map, show the places below reaching into it, so some addresses here may be served by them.
Places named: 1
- Evansville Wire-center boundary reaches this county FCC approved
Green Lake County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Green Lake County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Iowa County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Iowa County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Iron County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Iron County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Jackson County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Jackson County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Jefferson County
FCC approved
Shut-off authorized 265 days ago
- Filing / docket
- WC Docket 25-335
- Earliest shut-off
- On or after Nov 15, 2026
- Carrier
- AT&T
Places named: 3
- Fort Atkinson FCC approved
- Jefferson FCC approved
- Whitewater Wire-center boundary reaches this county FCC approved
Juneau County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Juneau County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Kenosha County
FCC approved
Shut-off authorized 265 days ago
- Filing / docket
- WC Docket 25-335
- Earliest shut-off
- On or after Nov 15, 2026
- Carrier
- AT&T
Places named: 1
- Somers FCC approved
Kewaunee County
FCC approved
Shut-off authorized 265 days ago
- Filing / docket
- WC Docket 25-335
- Earliest shut-off
- On or after Nov 15, 2026
- Carrier
- AT&T
Places named: 2
- Algoma FCC approved
- Kewaunee FCC approved
La Crosse County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in La Crosse County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Lafayette County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Lafayette County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Langlade County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Langlade County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Lincoln County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Lincoln County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Manitowoc County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Manitowoc County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Marathon County
FCC approved
Shut-off authorized 265 days ago
- Filing / docket
- WC Docket 25-335
- Earliest shut-off
- On or after Nov 15, 2026
- Carrier
- AT&T
No wire center, exchange or city named in a filing is in Marathon County itself. The Census blocks in the application, or the state's telephone exchange map, show the places below reaching into it, so some addresses here may be served by them.
Places named: 1
- Stevens Point Wire-center boundary reaches this county FCC approved
Marinette County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Marinette County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Marquette County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Marquette County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Menominee County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Menominee County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Milwaukee County
FCC approved
Shut-off authorized 265 days ago
- Filing / docket
- WC Dockets 25-335, 26-192
- Earliest shut-off
- On or after Oct 16, 2026
- Carrier
- AT&T
Places named: 2
- Milw Park Place FCC approved
- Milwaukee Fairway Filed
Monroe County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Monroe County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Oconto County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Oconto County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Oneida County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Oneida County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Outagamie County
FCC approved
Shut-off authorized 265 days ago
- Filing / docket
- WC Dockets 25-335, 26-192
- Earliest shut-off
- On or after Oct 16, 2026
- Carrier
- AT&T
Places named: 2
- Hortonville FCC approved
- Kaukauna Filed
Ozaukee County
FCC approved
Shut-off authorized 265 days ago
- Filing / docket
- WC Docket 25-335
- Earliest shut-off
- On or after Nov 15, 2026
- Carrier
- AT&T
No wire center, exchange or city named in a filing is in Ozaukee County itself. The Census blocks in the application, or the state's telephone exchange map, show the places below reaching into it, so some addresses here may be served by them.
Places named: 1
- Newburg Wire-center boundary reaches this county FCC approved
Pepin County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Pepin County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Pierce County
FCC approved
Shut-off authorized 265 days ago
- Filing / docket
- WC Docket 25-335
- Earliest shut-off
- On or after Nov 15, 2026
- Carrier
- AT&T
Places named: 2
- Ellsworth FCC approved
- River Falls FCC approved
Polk County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Polk County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Portage County
FCC approved
Shut-off authorized 265 days ago
- Filing / docket
- WC Docket 25-335
- Earliest shut-off
- On or after Nov 15, 2026
- Carrier
- AT&T
Places named: 2
- Stevens Point FCC approved
- Waupaca Wire-center boundary reaches this county FCC approved
Price County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Price County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Racine County
FCC approved
Shut-off authorized 265 days ago
- Filing / docket
- WC Docket 25-335
- Earliest shut-off
- On or after Nov 15, 2026
- Carrier
- AT&T
Places named: 2
- Caledonia FCC approved
- Big Bend Wire-center boundary reaches this county FCC approved
Richland County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Richland County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Rock County
FCC approved
Shut-off authorized 265 days ago
- Filing / docket
- WC Dockets 25-228, 25-335, 26-192
- Earliest shut-off
- On or after Jun 30, 2026
- Carrier
- AT&T
Places named: 3
- Evansville FCC approved
- Janesville Filed
- Whitewater Wire-center boundary reaches this county FCC approved
Rusk County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Rusk County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Sauk County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Sauk County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Sawyer County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Sawyer County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Shawano County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Shawano County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Sheboygan County
FCC approved
Shut-off authorized 265 days ago
- Filing / docket
- WC Dockets 25-335, 26-192
- Earliest shut-off
- On or after Oct 16, 2026
- Carrier
- AT&T
Places named: 1
- Sheboygan Falls FCC approved
St. Croix County
FCC approved
Shut-off authorized 265 days ago
- Filing / docket
- WC Docket 25-335
- Earliest shut-off
- On or after Nov 15, 2026
- Carrier
- AT&T
Places named: 3
- Houlton FCC approved
- Roberts FCC approved
- River Falls Wire-center boundary reaches this county FCC approved
Taylor County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Taylor County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Trempealeau County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Trempealeau County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Vernon County
FCC approved
Shut-off authorized 265 days ago
- Filing / docket
- WC Docket 25-335
- Earliest shut-off
- On or after Nov 15, 2026
- Carrier
- AT&T
Places named: 1
- Genoa City FCC approved
Vilas County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Vilas County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Walworth County
FCC approved
Shut-off authorized 265 days ago
- Filing / docket
- WC Docket 25-335
- Earliest shut-off
- On or after Nov 15, 2026
- Carrier
- AT&T
Places named: 2
- Whitewater FCC approved
- Williams Bay FCC approved
Washburn County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Washburn County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Washington County
FCC approved
Shut-off authorized 265 days ago
- Filing / docket
- WC Docket 25-335
- Earliest shut-off
- On or after Nov 15, 2026
- Carrier
- AT&T
Places named: 1
- Newburg FCC approved
Waukesha County
FCC approved
Shut-off authorized 265 days ago
- Filing / docket
- WC Dockets 25-335, 26-192
- Earliest shut-off
- On or after Oct 16, 2026
- Carrier
- AT&T
Places named: 2
- Big Bend FCC approved
- Sussex Filed
Waupaca County
FCC approved
Shut-off authorized 265 days ago
- Filing / docket
- WC Docket 25-335
- Earliest shut-off
- On or after Nov 15, 2026
- Carrier
- AT&T
Places named: 1
- Waupaca FCC approved
Waushara County
FCC approved
Shut-off authorized 265 days ago
- Filing / docket
- WC Docket 25-335
- Earliest shut-off
- On or after Nov 15, 2026
- Carrier
- AT&T
No wire center, exchange or city named in a filing is in Waushara County itself. The Census blocks in the application, or the state's telephone exchange map, show the places below reaching into it, so some addresses here may be served by them.
Places named: 1
- Waupaca Wire-center boundary reaches this county FCC approved
Winnebago County
FCC approved
Shut-off authorized 265 days ago
- Filing / docket
- WC Dockets 25-228, 25-335, 26-143
- Earliest shut-off
- On or after Jun 30, 2026
- Carrier
- AT&T
Places named: 4
- Neenah Filed
- Omro FCC approved
- Winneconne FCC approved
- Van Dyne Wire-center boundary reaches this county FCC approved
Wood County
Not named in any filing
No FCC discontinuance filing loaded here names a wire center in Wood County. It sits inside the AT&T footprint (Confirmed: FCC approved), so see the state summary for program-level status. Not named does not mean not at risk: filings arrive wire center by wire center.
Life-safety lines on copper here
Fire alarm panels, elevator phones and alarm transmitters must keep a compliant path after copper is discontinued. BCN POTS Over LTE is permitted under NFPA 72, UL Listed, approved for fire/life-safety incl. elevators & alarm panels, HIPAA, PCI and FCC compliant.
Status by county
27 counties in Wisconsin have at least one wire center named in a filing. Select a county to see its wire centers.
| County | Status | Places named | Earliest shut-off | Docket |
|---|---|---|---|---|
| Brown | FCC approved | 3 | On or after Mar 3, 2026 | WC Dockets 25-327, 26-143, 26-192 |
| Calumet Wire-center boundary reaches this county | Filed | 1 | On or after Oct 16, 2026 | WC Docket 26-192 |
| Columbia | FCC approved | 1 | On or after Jun 30, 2026 | WC Docket 25-228 |
| Dane | FCC approved | 3 | On or after Jun 30, 2026 | WC Dockets 25-228, 25-335, 26-192 |
| Dodge | FCC approved | 4 | On or after Nov 15, 2026 | WC Docket 25-335 |
| Fond du Lac | FCC approved | 1 | On or after Jun 30, 2026 | WC Docket 25-228 |
| Green Wire-center boundary reaches this county | FCC approved | 1 | On or after Jun 30, 2026 | WC Docket 25-228 |
| Jefferson | FCC approved | 3 | On or after Nov 15, 2026 | WC Docket 25-335 |
| Kenosha | FCC approved | 1 | On or after Nov 15, 2026 | WC Docket 25-335 |
| Kewaunee | FCC approved | 2 | On or after Nov 15, 2026 | WC Docket 25-335 |
| Marathon Wire-center boundary reaches this county | FCC approved | 1 | On or after Nov 15, 2026 | WC Docket 25-335 |
| Milwaukee | FCC approved | 2 | On or after Oct 16, 2026 | WC Dockets 25-335, 26-192 |
| Outagamie | FCC approved | 2 | On or after Oct 16, 2026 | WC Dockets 25-335, 26-192 |
| Ozaukee Wire-center boundary reaches this county | FCC approved | 1 | On or after Nov 15, 2026 | WC Docket 25-335 |
| Pierce | FCC approved | 2 | On or after Nov 15, 2026 | WC Docket 25-335 |
| Portage | FCC approved | 2 | On or after Nov 15, 2026 | WC Docket 25-335 |
| Racine | FCC approved | 2 | On or after Nov 15, 2026 | WC Docket 25-335 |
| Rock | FCC approved | 3 | On or after Jun 30, 2026 | WC Dockets 25-228, 25-335, 26-192 |
| Sheboygan | FCC approved | 1 | On or after Oct 16, 2026 | WC Dockets 25-335, 26-192 |
| St. Croix | FCC approved | 3 | On or after Nov 15, 2026 | WC Docket 25-335 |
| Vernon | FCC approved | 1 | On or after Nov 15, 2026 | WC Docket 25-335 |
| Walworth | FCC approved | 2 | On or after Nov 15, 2026 | WC Docket 25-335 |
| Washington | FCC approved | 1 | On or after Nov 15, 2026 | WC Docket 25-335 |
| Waukesha | FCC approved | 2 | On or after Oct 16, 2026 | WC Dockets 25-335, 26-192 |
| Waupaca | FCC approved | 1 | On or after Nov 15, 2026 | WC Docket 25-335 |
| Waushara Wire-center boundary reaches this county | FCC approved | 1 | On or after Nov 15, 2026 | WC Docket 25-335 |
| Winnebago | FCC approved | 4 | On or after Jun 30, 2026 | WC Dockets 25-228, 25-335, 26-143 |
Not named in any filing loaded here: Adams, Ashland, Barron, Bayfield, Buffalo, Burnett, Chippewa, Clark, Crawford, Door, Douglas, Dunn, Eau Claire, Florence, Forest, Grant, Green Lake, Iowa, Iron, Jackson, Juneau, La Crosse, Lafayette, Langlade, Lincoln, Manitowoc, Marinette, Marquette, Menominee, Monroe, Oconto, Oneida, Pepin, Polk, Price, Richland, Rusk, Sauk, Sawyer, Shawano, Taylor, Trempealeau, Vilas, Washburn, Wood.
Key national deadlines
-
Done
FCC cuts the required copper-retirement customer notice period from 180 days to 90 days.
-
Done
Lumen stops accepting new & move/add/change POTS orders across its 14-state legacy CenturyLink/Qwest territory.
-
Done
AT&T stops accepting new copper POTS orders across ~20 states in its ILEC footprint.
-
Done
AT&T files FCC discontinuance application covering ~90,000 customers across 18 states.
-
Done
FCC grants AT&T's 18-state application, over 30% of its copper footprint outside California.
-
Done
FCC adopts the Network and Services Modernization Order (FCC-26-19A1), streamlining Section 214 nationwide.
-
Done
AT&T begins physically decommissioning ~500 wire centers (~10% of its footprint).
-
Done
FCC approves AT&T's California discontinuance application covering 184,000+ locations.
-
Done
Deadline: permanent copper discontinuance for ~90,000 AT&T customers across 18 states.
-
Upcoming
Earliest date AT&T can begin discontinuing California copper service (184,000 locations).
-
Upcoming
AT&T's target to retire the large majority of its copper footprint outside California.
If your lines are in a named wire center
Move fire alarm, elevator and voice lines off copper before the carrier does it for you.
BCN POTS Over LTE keeps legacy panels working over a managed LTE connection with battery backup, on a single invoice for every location. BCN also offers Cloud Voice (UCaaS), SIP/SIP PRI and Cable Voice where a full voice migration makes more sense.
BCN POTS Over LTE
- Fully monitored and managed
- MFVN-compliant ATA, up to 8 lines per device
- Dual-SIM 4G LTE with optional wired redundancy
- 8-hour battery backup (24-hour optional)
- Supports fax (T.38), modem, alarm transmitters, elevator phones
- White-glove installation with post-install test report
- Permitted under NFPA 72
- UL Listed
- Approved for fire/life-safety incl. elevators & alarm panels
- HIPAA, PCI and FCC compliant
Source: BCN POTS Over LTE Solution Overview; BCN POTS Replacement Solutions Overview
Latest coverage from carriers and the FCC
-
Data Center Dynamics
Nvidia looks to tap Brightspeed central offices for inference network - report
-
Data Center Dynamics
AT&T copper retirement pushes on as carrier reveals just 1% still using legacy technology
-
Light Reading
AT&T copper network retirement set to accelerate as legacy base shrinks to 1%
-
Broadband Breakfast
-
DataRemote
-
Fusion Connect
FCC Unanimously Clears a Faster Path to Retire Copper Networks
-
Broadband Breakfast
-
FCC
Network and Services Modernization Order (FCC 26-19), full text
-
Broadband Breakfast
AT&T Approved to Discontinue Service at More Than 30% of Copper Footprint This Year
-
Light Reading
-
Fierce Network
Authoritative sources
Use these sources to discover and verify retirement records. A published deadline should be tied to the underlying carrier/FCC/state notice, not this source list alone.
-
FCC
FCC Electronic Comment Filing System (ECFS)
Search carrier filings and proceedings involving copper retirement and network changes
1 - Primary
Weekly
-
FCC
FCC Wireline Competition Bureau
Monitor wireline public notices, orders, and policy updates
1 - Primary
Weekly
-
FCC
Confirm governing network-change and copper-retirement notification rules, especially §51.333
1 - Primary
Quarterly
-
Verizon
Verizon Network Disclosures 2025-2026
Find current copper-retirement disclosures by state and notice
1 - Primary
Weekly
-
Verizon
Verizon Partner Solutions Network Events
Monitor copper retirements, switch retirements, and other network events
1 - Primary
Weekly
-
Verizon
Verizon Network Disclosures 2022-2024 Archive
Research historical copper-retirement notices
2 - Supporting
As needed
-
Lumen / CenturyLink / Qwest
CenturyLink/Lumen Network Disclosures
Find current copper-retirement notices, wire centers, CLLIs, issue dates, and effective dates
1 - Primary
Weekly
-
Lumen / CenturyLink / Qwest
CenturyLink Active Network Disclosure Archive
Research historical network disclosures
2 - Supporting
As needed
-
Lumen / CenturyLink / Qwest
CenturyLink Wholesale Network Disclosures
Research older wholesale and FCC network-change notices
2 - Supporting
Monthly
-
Frontier
Frontier Copper Optimization / Copper Retirement Notices
Find centralized copper-retirement notices by market or state
1 - Primary
Weekly
-
Frontier
Monitor current copper and switch-retirement notices
1 - Primary
Weekly
-
Frontier
Research prior-year copper and switch-retirement notices
2 - Supporting
As needed
-
AT&T
AT&T Regulatory Documents / Tariffs
Find state-specific tariffs, service withdrawals, and wire-center records
1 - Primary
Weekly
-
AT&T
FCC ECFS Search for AT&T Filings
Verify AT&T network-change and copper-retirement filings
1 - Primary
Weekly
-
State Commissions
NARUC State Regulatory Commission Directory
Locate the applicable PUC, PSC, or BPU for state-level verification
1 - Primary
Monthly
-
Windstream / Kinetic
Locate official network-change filings when no centralized carrier page is available
1 - Primary
Weekly
-
Consolidated / Fidium
Locate official network-change filings when no centralized carrier page is available
1 - Primary
Weekly
-
Other / Smaller ILECs
NARUC State Regulatory Commission Directory
Find the appropriate state regulator for carriers without a centralized disclosure page
1 - Primary
Monthly
-
All Carriers
Direct Carrier / Wholesale Partner Notices
Capture circuit- or location-specific deadlines received directly from a carrier
1 - Primary
As received
Talk to BCN about POTS replacement
About: Douglas County, WI (0 wire centers). BCN will confirm whether your service addresses fall inside an affected wire center.